151st, Black Bob to 1800' South

Project Number: 3-C-067-11

Project Location/Limits:
151st, Black Bob to 1800' South

Project Scope:
Improvememts will include reconstruction of a 1800' section of Black Bob Road to full capacity.  The improvements will also include right and dual-left turn lanes at each leg of the intersection of 151st & Black Bob and a new traffic signal approximately 900' south of 151st Street.  The project will include storm sewer, medians, lighting, landscaping, and sidewalks.

Current Project Status:
O'Donnel and Sons Construction along with Olsson Associates have been hired to complete this project as a design build.  The project is currently under construction.

Construction began in April of 2013 and is tentatively schedule to be complete in the fall.

Total Project Cost: $400,000

For more information regarding this project: