151st & Mur-Len Geometric Improvements with Signal

Project Number: 3-C-105-12

Project Location/Limits:
151st & Mur-Len Geo Imp with Signal

Project Scope:
Construct right turn lanes for the north, south, east and westbound movements at the intersection, and close and/or relocate private driveways near the intersection. Replace existing outdated traffic signal to make it able to tie into the new ATMS.

Current Project Status:
Affinis has been hired to complete the design for this project. Currently, construction on this project is not scheduled to begin until 2018.

Total Project Cost: $3,300,000

For more information regarding this project: