Project Number: 1-R-000-11
Project Location/Limits:
2011 Sewer Maintenance CIPP
Project Scope:
This project is part of the annual Sanitary Sewer Maintenance Inflow & Infiltration (I&I) Reduction Program in the Capital Improvement Program (CIP). This program was established to reduce the amount of I&I entering the sanitary sewer system. The overall goal is to reduce the amount of I&I in the sanitary sewer flow for treatment at the City’s Wastewater Treatment Plants and to the Johnson County Wastewater Treatment Plant. This project will include the installation of Cured-In-Place-Pipe (CIPP) for 13,386 lineal feet of gravity sanitary sewer mains throughout the city to reduce inflow, infiltration, and restore structural integrity.
Current Project Status:
This project began in September and will be finished by the end of 2011.
Total Project Cost: $300,000
Project Contact: Rebecca Bilderback (913) 971-9116