2013 Cedar Creek Street Improvments, 110th Terrace

Project Number: 3-R-001-13

Project Location/Limits:
2013 Cedar Creek Street Improvments, 110th Terrace

Project Scope:
Reconstruction of 110th Terrace from Cedar Niles Boulevard to the west end cul-de-sac. Project includes removal of existing concrete street and replacment with asphalt pavment, concrete curb and gutter, ADA sidewalk ramps and replacment of broken or detriorating sidewalk. Project is authorized as part of the 2013 Street Reconstruction Program.

Current Project Status:
Currently in construction with completion scheduled for August 2013.

Project Contact: 913-971-9050