Cedar Creek Wastewater Treatment Plant

Project Number: 1-C-004-07

Project Location/Limits:
Cedar Creek Wastewater Treatment Plant

Project Scope:
The CCWWTP expansion project is planned to keep up with the growing City wastewater treatment volumes, and also address regulatory requirements. The expansion includes provisions for biological nutrient removal (BNR), which will provide mechanisms for reduction of both nitrogen and phosphorus from the plant effluent.

Current Project Status:
Currently under construction. Completion scheduled for Summer of 2012.

Total Project Cost: $46,000,000

Project Contact: Randy Freeman, (913) 971-9065