Project Number: 3-C-044-07
Project Location/Limits:
Old 56 Bridge over Cedar Creek
Project Scope:
Removal and replacement of the existing bridge over Cedar Creek. The current bridge will be replaced with a new four lane bridge with 6 foot shoulders.
Current Project Status:
George Butler Associates is currently working on the design of this project. It is anticipated that construction will begin in the Spring of 2009.
Total Project Cost: $2,243,000.00
Project Contact: Therese Mersmann, (913)971-8752, tmesmann@olatheks.org
Last Updated: December 01, 2008
![]() |
![]() |