South Cedar Creek Sewer Phase II & III

Project Number: 1-B-086-10

Project Location/Limits:
South Cedar Creek Sewer Phase II & III

Project Scope:
The project includes the construction of sanitary sewer gravity pipes extending from the north side of 167th and Hedge Lane extending along the west side of the property owned by Hedge 175 and Associates, LLC (Ken Block) and south under 175th Street.

Current Project Status:
Holthouse Construction began this work in summer 2011 and expects to complete the project by the end of the year.

Total Project Cost: $2,354,856

Project Contact: Rebecca Bilderback (913) 971-9116