127th Street Improvement Project Enters Final Phase of Construction

Construction on the 127th Street Improvement project is on schedule and projected to be substantially complete in August 2014, weather permitting. Beginning the week of June 2, 127th Street will be closed from Hallet to Gallery. The street will also remain closed from Gallery to Pflumm.

Visitors to St. Andrews Christian Church will have a signed detour starting at Greenwood that directs travelers through the Eastbrooke neighborhood. 

As part of this project, Pvlumm Road will continue to be reduced to one lane in each direction. Beginning Thursday, June 5, the contractor will open the right through lanes and close the left lanes for left turn lane construction at this intersection. The work on Pflumm Road is planned to completed in June, weather permitting. Closures west of Pflumm Road on 127th Street will remain through August. 

For updates on construction projects throughout Olathe, please visit the Construction Projects Map